CitiPower
VIC — Melbourne CBD and inner suburbs. 10 clause-level requirements, each mapped to a primary source.
At a glance
- Network
- CitiPower
- State
- VIC
- Connection portal
- CitiPower/Powercor eConnect
- Pre-approval
- Required before install
- Typical timeframe
- 5–15 business days
- Static export limit
- single-phase 5 kW; three-phase 5 kW per phase
- Flexible exports
- Up to 10 kW total across all phases — CitiPower/Powercor flexible exports — Offered after a pre-approval returns a 0 kW export limit — CitiPower/Powercor: "Eligible customers will be offered a flexible exports connection after lodging a pre-approval and receiving a 0kW export limit." The alternative is a 0 kW static limit. No rollout schedule is published.
- Zero export possible
- Yes
Clause-level requirements
Applies to all NEW rooftop solar systems ≤200 kW from 1 Oct 2024, AND to legacy systems that have an inverter replaced after 1 Oct 2024 — unless the replacement is like-for-like or under warranty.
Systems >200 kW: emergency backstop applies to all new, upgrading and replacement systems from 25 Oct 2023 (Stage 1).
Governing instrument: Stage 2 Ministerial Order (in effect Oct 2025, Vic Government Gazette GG2025S553) — REPLACES the previous Stage 2 Orders. Adds: legacy-system & battery clarifications; DNSP obligations to support installers incl. diagnostic information for failed testing; DNSP requirement to maintain operating utility servers and conduct network-wide testing; DAPR reporting additions.
Pre-approval connection application must be submitted to the distributor BEFORE installation (model standing offer flow); check product-list changes since initial sale.
Equipment must be CSIP-AUS compliant (or a compliant combination of equipment).
Inverter(s) must be connected to the internet and REMAIN connected for the entire registration and commissioning process — non-connected devices are the biggest cause of connectivity failure.
Configure the installation to communicate with the relevant distribution business's utility server; apply Australia A settings per the distributor's testing and commissioning process.
The commissioning test must be run during DAYLIGHT conditions — tests run at night or in low light will not pass.
Post-install: a licensed electrical inspector must conduct a safety check BEFORE the system generates; the system stays OFF until the inspection is approved and a Certificate of Electrical Safety is issued (the inspector turns the system on).
Post-install: notify the energy retailer and distribution business and submit required information for meter reconfiguration; the system is export-ready only when the distributor completes meter configuration and confirms connection.
Where the sources disagree
Sources
- Victorian backstop dates & CSIP-AUS requirement — accessed 2026-07-27
- Installer backstop guidance & commissioning — accessed 2026-07-27
- Flexible exports (up to 10 kW, real-time) — accessed 2026-08-30
- Stage 2 Ministerial Order (Oct 2025) — governing instrument, DNSP obligations — accessed 2026-07-28
- DEECA industry guidance — installer process, daylight testing, CoES sequencing — accessed 2026-07-28
Generated from data/networks/citipower.json. Every requirement above links to the
primary source it was read from, with the date it was read. Network requirements change — check the
linked source before relying on any line of this page. This page is decision support for a licensed
installer, not advice, and it is not published or endorsed by CitiPower.